A tightly compacted base layer, calculated from finished depth rather than loose material estimates.
Enter your project dimensions
Expect crusher run to shrink 10-15% as it is compacted from its loose truck depth. Ordering only to the finished measurement can leave the base half an inch shallow, so the calculator has its +10% allowance turned on. In Maine, Bank Run Gravel, pit gravel, Type D gravel, and 2-inch-minus material can refer to this product: crushed stone with fines included, at about 3,000 lb per cubic yard, forming a surface tires are less likely to push aside.
Calculate for finished depth
- First, find the footprint in feet. Multiply length by width for a lane, or use the pad measurements.
- Enter the required compacted depth for the finished layer: 4 inches for paths and pavers, 4-6 for driveways, and 6-8 beneath trucks.
- Find cubic feet / 27 = yards, then x 1.5 = tons, with the +10% allowance left on. Specifications refer to the layer after rolling.
Tons and coverage
| Compacted depth | 1 cubic yard covers | 1 ton covers |
|---|---|---|
| 2 inches | 162 sq ft | ≈ 108 sq ft |
| 4 inches | 81 sq ft | ≈ 54 sq ft |
| 6 inches | 54 sq ft | ≈ 36 sq ft |
| 8 inches | 41 sq ft | ≈ 27 sq ft |
Recommended uses and limits
- For a driveway base, compact 4-6 inches first. Finish with 2-3 inches of #57 or driveway gravel as the travel layer.
- For a low-cost camp road, crusher run by itself can form a usable surface. It will be dusty during summer and calls for regrading every 2-4 years.
- Build paver or slab bases to 4 inches, compacting in 2-inch layers. The Paver Base Calculator calculates the complete paver system.
- For equipment pads, place 4 inches over stripped ground, or 6 on soft soil.
- Keep crusher run out of a French drain. Its fines help it bind but also retain water; use clean #57 or drain rock where water needs to move through.
Example: a 20 x 10 parking pad
For two hundred square feet at a compacted 4 inches, calculate 200 x 0.333 = 67 cubic feet = 2.5 cubic yards, which is 3.7 tons. Include the allowance and plan on 4 tons. Put down half the material and compact it, then place the remaining half and compact once more. In Maine's freeze-thaw conditions, 2 lifts at 2 inches each hold up longer than a single 4-inch layer, and an afternoon plate-compactor rental costs less than repairing the first pothole.
Delivery guidance
- Schedule the base stone and surface stone together to keep work on track. Either option has free delivery.
- Have the load placed at the distant end, then work the material back toward the pile. On large pads, moving downhill instead of uphill can save a full day.
- Before compaction, lightly mist each lift. Damp crusher run tightens more than dry material.
- Leave a wheelbarrow-load aside for repairs. Road crews use this same material for potholes, and eventually you will need some too.
Pricing overview
Crusher run is made during crushing, unlike washed and sorted stone. Adding the +10% allowance to a 4-ton order can prevent the need for another half-ton delivery. Review the Crusher Run product page for its per-ton price, compare Road Base, and arrange both driveway layers with one free delivery.
Crusher run, Bank Run Gravel, pit gravel, and Type D gravel questions
How much crusher run is required for a driveway?
What is the weight of a yard of crusher run?
How do crusher run and gravel differ?
Are crush and run and crusher run identical?
Can crusher run serve as the top surface?
How much does crusher run shrink during compaction?